Nov 13th update
Only four gals left, but they work hard. As you can see the LR & kitchen are painted. All the ceilings are done after Tina found the paint roller ends so Mark could use the big roller. David Valkenaar (a civil engineer from San Mateo who knows Bill Hoeft) and John trimmed the sheet-rock around the windows so we can trim them.
We rented a floor sander and started in the Boys’ room. For those who were here in the beginning, believe me when I say it took half a day to sand and it is still not flat. Can’t wait to get in the LR. I hope Harley’s patch work is easier in the LR.
The siding crew turned the corner to the front porch and claim they need 2 more hours. Still waiting for the plumber to finish the MB tub. Will someone call Tony?
Cynthia loves the colors so far, thanks to Toby and ( I for get help pick them.) Still waiting for a color for Lilly’s room. Maybe Brittany will help her. Rudy is cooking B’fast tomorrow, you will be up by 7AM.