Nov 18th update…The Punch List

1. Siding on porch 1 day Doug & crew
2. Caulk porch 1 hour, need caulk
3. Prime porch 30 min
4. Paint porch 4 hr
5. Install screens 3 hr
6. Hang Interior doors 2 days 2 people need doors 12
7. Trim windows 2 days 2 people
8. Trim doors 1 day 2 people
9. Sand and varnish hardwood floors 1 day 1 person
10. Kitchen floor 3 days 2 people need thin set and grout
11. Bath floor 3 days 2 people need thin set and grout
12. Mud MB 2 hr 1 person
13. Trim base boards 1 day 2 people need trim
14. Build and install steps 1 day 3 people
15. Install floor in MBR and utility room 1 day 2 people need flooring
16. Install door hardware 10 hr 1 person
17. Paint MB 2 hr 1 person
18. Paint all trim and doors 1 day 3 people
19. Install attic stairs 2 people 1 hr
20. Finish electric electrician
21. Install vanity in MB 2 hr 1 person
22. Finish plumbing plumber?
23. Install upper cabinets 3 hr 2 people
24. Install lower cabinets 1 day 2 people waiting for arrival

VOLUNTEER TIME NEEDED TO COMPLETE THIS LIST: 1 person=36 days, 2 people=18 days, 4 people=9 days, and 6 people=6 days

I am now back at home. The only one there is David Valkenaar who is leaving Thanksgiving morning. He will do what he can with the help (I hope) of Eddie. David please send an update. And thanks for being the last one standing. I will be back Nov 28th with as many volunteers as we can find.